Irrigation Minister Sets Firm Timelines for Palamuru Project Completion

Hyderabad: In a significant push to accelerate infrastructure development, Irrigation Minister N. Uttam Kumar Reddy has mandated that officials prepare comprehensive, time-bound implementation plans for the Palamuru irrigation projects, emphasizing the urgency of delivering these long-delayed schemes.
During a high-level meeting held on Monday, the minister stressed that all deadlines are non-negotiable and called for swift execution of the decisions reached during the recent two-day tour of Palamuru and the Chief Minister's site inspections.
The minister has instructed officials to address critical bottlenecks including land acquisition challenges, rehabilitation and resettlement matters, electricity supply issues, and contractor accountability with utmost priority. He emphasized that the state has entered a phase of rapid implementation and remains dedicated to completing irrigation projects that would serve millions of farmers across the region.
Key project milestones established
The Mahatma Gandhi Kalwakurthy Lift Irrigation Scheme must see completion of pumping station repairs and rehabilitation by March 2027, according to the minister's directives. Work on the canal infrastructure associated with the Narlapur Reservoir should be finished, with the entire project including the canal network operational by June 2027.
For the Palamuru-Rangareddy Lift Irrigation Scheme, officials have been instructed to expedite resettlement of families displaced by the Narlapur, Yedula and Uddandapur reservoirs. The main trunk infrastructure reaching Karivena Reservoir must be completed by December 2026, while immediate power connections to the Narlapur, Yedula and Vattem pump stations are essential.
The minister also directed a feasibility study into solar power generation at reservoir sites to help reduce long-term energy expenditures.
Additional schemes accelerated
Under the Makthal-Narayanpet-Kodangal Lift Irrigation Scheme, land acquisition proceedings for approximately 2,200 acres should commence by July 2026. Officials have also been tasked with completing acquisition and rehabilitation processes for roughly 4,200 acres already under notification and accelerating Phase-I implementation.
For the Jawahar Nettampadu Lift Irrigation Scheme, the minister instructed rapid acquisition of 534 acres to unlock irrigation potential for an additional 58,000 acres.
The minister additionally reviewed proposals to increase Gudemdoddi Reservoir's storage capacity to 15 TMC and directed officials to examine the feasibility of establishing solar power installations near pump stations.
Chief Engineers have been ordered to submit detailed completion timelines for all major project components, while District Collectors must pursue land acquisition through negotiated settlements wherever feasible and guarantee timely distribution of rehabilitation assistance to affected families.