Mechanical Seal Retrofit Slashes Water Consumption at Copper Mine's Critical Tailings Pump

June 1, 2026

A major copper mining operation has achieved significant water savings through a mechanical seal retrofit on a critical tailings pump, marking a shift toward more sustainable and reliable equipment maintenance practices.

John Crane, part of the Smiths Group plc conglomerate and a specialist in flow control technologies, engineered and installed the retrofit on a Warman 550 underflow thickener pump operating at approximately 65% solids density. The modification replaced the pump's traditional stuffing box arrangement with a modern mechanical seal system, reducing the volume of clean water required for sealing operations from around 20 cubic metres per hour to between 7.5 and 8 cubic metres per hour.

This translates to a daily water conservation of approximately 288,000 litres—a substantial reduction that reflects both environmental and operational benefits for the mining facility.

Underflow thickener pumps serve as essential components in tailings management systems, transporting high-density slurry from thickening vessels into tailings transport infrastructure. Any production interruption on these pumps creates immediate operational consequences, making reliability paramount.

Before the retrofit, the facility experienced accelerated wear on the pump's shaft sleeve due to the abrasive nature of the service environment. Replacement of the sleeve was required approximately every four months, necessitating major maintenance events. These interventions demanded a full mechanical crew working across two shifts—roughly 36 hours of labour—along with deployment of a 100-tonne crane and significant exposure to safety and production risks.

The retrofit design incorporated a controlled seal-flush arrangement using diamond-faced materials, engineered to maintain a clean operating environment at the seal faces even if flush pressure drops and solids breach the seal chamber. An adapter sleeve was custom-fabricated to suit the existing shaft, allowing installation without requiring pump modifications.

Following commissioning, the retrofitted pump has performed reliably. The seal-flush system was configured for approximately 11 cubic metres per hour at 75 psi, though actual operating conditions have shown consumption of 7.5 to 8 cubic metres per hour.

The retrofit design aligns maintenance scheduling with the site's existing annual major service interval, when the impeller and rubber liners are routinely replaced. This approach eliminates the need for additional unplanned maintenance interventions throughout the year, creating more predictable operational cycles.

Warren Smith, Global Mining Market Director at John Crane, noted the significance of the project: "Underflow thickener pumps rank among the most critical assets within a mine's tailings circuit, so operators naturally approach modifications with caution. This installation demonstrates how advanced sealing technology can reduce maintenance demands and lower clean water consumption, while enabling more structured planned maintenance schedules."

The installation represents a notable achievement for John Crane. With a shaft diameter of approximately 270 millimetres, the seal ranks as the largest slurry seal the company has supplied to date.